Communication Plan: Drop — Fintech Payment App
Communication Plan: Drop — Fintech Payment App
Project: Drop — Remittance + QR Payments
Version: 1.0
Date: 2026-02-23
Author: John (AI Director)
Status: Approved
Reviewers: Alem Bašić (CEO)
Document History
| Version |
Date |
Author |
Changes |
| 0.1 |
2026-02-23 |
John |
Initial draft — Drop-specific communication structure |
1. Communication Objectives
Drop is an AI-native internal product of ALAI Holding AS. Communication is primarily between John (AI Director) and Alem Bašić (CEO), with AI agents reporting asynchronously. Objectives:
- Transparency — Alem always knows Drop status, blockers, and decisions at a glance
- Alignment — Requirements and priorities confirmed before implementation begins
- Accountability — Blockers surfaced immediately; decisions recorded in
comms/decisions/
- Regulatory readiness — All compliance-relevant decisions documented for Finanstilsynet
- Documentation — Drop is AI-native; decisions persist in comms/decisions/ and HiveMind
2. Stakeholder Communication Needs
| Stakeholder |
Role |
Information Needs |
Channel |
Frequency |
Detail Level |
| Alem Bašić |
CEO / Sponsor |
Milestone status, budget, strategic risks, partner decisions |
Direct session |
Weekly + ad-hoc |
Executive summary |
| John |
AI Director |
Full project status, risks, agent output, technical decisions |
Mission Control |
Daily |
Detailed |
| AI Builder agents |
Implementers |
Task specs, acceptance criteria, schema refs |
Task prompt |
Per-task |
Technical |
| AI Validator agents |
QA |
Feature to validate, test criteria, DoD |
Task prompt |
Per-task |
Technical |
| SpareBank1 / BaaS partners |
External partners |
Drop capabilities, partnership terms |
Email via Alem |
Quarterly + as needed |
Executive |
| Finanstilsynet |
Regulator |
PISP/AISP registration documentation |
Formal submission |
Annual + milestones |
Formal |
| Waitlist users |
Early adopters |
Launch updates, beta invitations |
Email ([email protected]) |
Monthly |
Simple |
| Local merchants |
Merchant users |
Onboarding, QR setup, fee structure |
In-person + email |
On onboarding |
Simple |
3. Communication Channels & Tools
4. Meeting Schedule
4.1 Regular Ceremonies (AI-Native Cadence)
| Meeting |
Purpose |
Frequency |
Format |
Facilitator |
Output |
| Sprint Planning |
Backlog review, task assignment to agents |
Every 2 weeks |
Async (John prepares) + Alem review |
John |
Sprint tasks in Mission Control |
| Sprint Review |
Demo completed features |
Every 2 weeks |
Alem session — John demos |
John |
Sprint log entry in PIPELINE.md |
| Sprint Retrospective |
Process improvement, learning opportunity |
Every 2 weeks |
Async by John + /learning-opportunity |
John |
Updated MEMORY.md / rules |
| Weekly Status Check |
Drop status for Alem |
Weekly |
Written status in HiveMind + direct session if needed |
John |
Status report |
| Risk Review |
Update risk register |
Weekly |
Embedded in sprint planning |
John |
Updated risk-register.md |
| Strategic Review |
Partner decisions, regulatory updates |
Monthly |
Alem session |
Alem |
Decision record |
4.2 Event-Triggered Communications
| Trigger |
Action |
Channel |
Response Time |
| New critical risk (Score ≥ 15) |
Escalate to Alem |
Direct session |
Within 4 hours |
| Security incident |
Incident report + Alem notification |
Direct + email |
Immediately |
| BaaS partner response received |
Alem briefing + decision session |
Direct session |
Within 24 hours |
| Milestone completed |
Update PIPELINE.md + notify Alem |
HiveMind post |
Same day |
| Finanstilsynet correspondence |
Legal review + Alem briefing |
Direct + email |
Within 48 hours |
| Agent task failure / blocked |
John investigation + Alem if strategic |
Mission Control |
Within 4 hours |
5. Reporting Cadence
| Report |
Frequency |
Prepared By |
Audience |
Location |
| Sprint Report |
Per sprint |
John |
Alem |
PIPELINE.md sprint log |
| Weekly Status |
Weekly |
John |
Alem |
HiveMind + direct session |
| Risk Report |
Monthly |
John |
Alem |
risk-register.md |
| Budget Report |
Monthly |
Finance agent |
Alem |
comms/reports/ |
| Milestone Report |
Per milestone |
John |
Alem + partners |
PIPELINE.md + email |
| Security Report |
Per sprint |
Security agent |
John + Alem |
security/ directory |
| Post-launch Report |
30 days post-launch |
John |
Alem + investors |
comms/reports/ |
5.1 Weekly Status Template
SUBJECT: Drop — Weekly Status — Week of [DATE]
STATUS: ON TRACK / AT RISK / DELAYED
PHASE: [Current phase from ROADMAP.md]
STAGING: https://drop-staging.fly.dev/ — [UP/DOWN]
THIS WEEK:
- [completed item 1]
- [completed item 2]
NEXT WEEK:
- [planned item 1]
- [planned item 2]
BLOCKERS:
- [blocker] → [action needed from Alem]
TOP RISKS:
| Risk | Score | Status |
|------|-------|--------|
| [R-001] BaaS partner | 20 | [current status] |
DECISIONS NEEDED FROM ALEM:
- [ ] [decision by date]
6. Escalation Paths
| Level |
Trigger |
Escalate To |
Channel |
Response SLA |
| L1 |
Agent blocker (technical) |
John (self-resolve) |
Mission Control |
4 hours |
| L2 |
Architecture decision required |
John (makes decision) |
ADR in comms/decisions/ |
Same day |
| L3 |
Strategic / partnership decision |
Alem |
Direct session |
24 hours |
| L4 |
Budget change > 10% |
Alem |
Direct session |
24 hours |
| L5 |
Legal / regulatory blocker |
Alem + external legal |
Email + direct |
48 hours |
| P1 |
Security incident / data breach |
Alem immediately |
Direct + email |
15 minutes |
7. Documentation Standards
7.1 File Naming Convention
[DOCUMENT_TYPE]-[DATE]-[VERSION].[ext]
Example: drop-sprint-report-2026-02-20-v1.0.md
Example: drop-meeting-notes-2026-02-20.md
7.2 Document Storage Locations
| Document Type |
Location |
| Project governance (charter, brief, RACI, risks) |
docs/PROJECT-GOVERNANCE/ |
| Business requirements |
docs/BUSINESS-REQUIREMENTS/ |
| Decision records / ADRs |
comms/decisions/ |
| Meeting notes |
comms/meetings/ |
| Status reports |
comms/reports/ |
| Partner communications |
comms/client/ |
| Technical documentation |
docs/ (see INDEX.md) |
| Security reports |
security/ |
7.3 Decision Record Format (ADR)
All significant decisions must be logged in comms/decisions/ as ADR files:
# ADR-XXX: [Decision Title]
**Date:** YYYY-MM-DD
**Status:** Proposed | Accepted | Deprecated | Superseded
**Decider:** [Name/Agent]
**Context:** [Why this decision was needed]
**Decision:** [What was decided]
**Consequences:** [What changes as a result]
**Alternatives considered:** [What else was evaluated]
8. External Communication Protocols
| Communication Type |
Authorized |
Approval Required |
Notes |
| BaaS partner updates |
Alem |
None |
Document outcomes |
| Finanstilsynet submissions |
Alem + Legal advisor |
Alem sign-off |
Formal; keep copies |
| Press / public statements about Drop |
Alem only |
Alem |
No product details without approval |
| Merchant onboarding comms |
Alem |
None |
Track in merchant dashboard |
| Waitlist email updates |
John |
Alem approval for major announcements |
Via MCP email — info account |
| Investor communications |
Alem |
Alem |
John prepares materials |
9. Crisis Communication Plan
9.1 Crisis Triggers
- Production security breach or data exposure
- Payment processing failure affecting users
- Regulatory action or investigation by Finanstilsynet
- BaaS partner contract failure
-
4-week unplanned delay to any Phase 2+ milestone
9.2 Crisis Protocol
- Identify — John identifies crisis; logs in
project/docs/incident-report.md
- Contain — John assesses scope and implements immediate mitigations (within 1 hour)
- Escalate — John notifies Alem via direct session within 1 hour of identification
- Communicate — John drafts external communication; Alem approves before sending
- Update — Alem and affected parties receive updates every 4 hours until resolved
- Resolve — Crisis closed when all impacts mitigated and systems restored
- Learn —
/learning-opportunity skill run; memory updated; process improved
9.3 Crisis Communication Template
SUBJECT: [DROP — URGENT] [Crisis Summary]
Vi vil informere deg om en situasjon som påvirker Drop.
SITUASJON: [What happened]
PÅVIRKNING: [What is affected]
UMIDDELBARE TILTAK: [What we have done]
NESTE STEG: [What we will do]
FORVENTET LØSNING: [Timeline]
Neste oppdatering: [Next update time]
Kontakt: Alem Bašić — [email protected] — +47 40 47 42 51
Approval
| Role |
Name |
Date |
Signature |
| Author |
John (AI Director) |
2026-02-23 |
Approved (AI) |
| AI Director (John) |
John |
2026-02-23 |
Approved |
| CEO / Project Sponsor |
Alem Bašić |
TBD |
|