Rollback Plan

Rollback Plan

Project: Bilko Version: 0.1 Date: 2026-02-23 Author: Ops Architect Status: Draft Reviewers: Tech Lead, Alem Bašić

Document History

Version Date Author Changes
0.1 2026-02-23 Ops Architect Initial draft

1. Overview

This document defines the rollback procedure for Bilko deployments. A rollback restores the production environment to the previous working state when a deployment causes critical issues.

Rollback authority: Alem Bašić (primary). Any engineer can initiate rollback for P0 issues. Target rollback time: < 5 minutes for frontend, < 10 minutes for backend, < 60 minutes for database


2. Rollback Decision Criteria

Automatic Rollback Triggers

Initiate rollback immediately without waiting:

  • Health check https://api.bilko.io/health returns non-200 for > 3 consecutive minutes
  • Error rate > 5% of all API requests (Sentry)
  • Any financial calculation producing provably incorrect results (VAT, double-entry)
  • Authentication completely broken (no user can log in)
  • Database migrations caused data corruption

Manual Rollback Triggers (Alem Bašić decision)

  • P99 latency > 5s sustained for > 5 minutes
  • Critical feature broken with no quick fix available
  • Security vulnerability discovered in new release
  • User-reported data loss

Do NOT Roll Back For

  • Performance degradation < 20% (investigate first)
  • Non-critical feature broken with workaround available
  • Minor UI regressions
  • Single user reporting an issue (investigate first)

3. Rollback Procedures by Component

3.1 Frontend Rollback (Vercel) — < 5 minutes

Vercel keeps all previous deployments. Rollback is instant (no rebuild).

Via Vercel Dashboard (recommended):

  1. Open https://vercel.com/alai/bilko/deployments
  2. Find the last successful deployment (before current broken one)
  3. Click "..." → "Promote to Production"
  4. Wait 30 seconds for propagation
  5. Verify: curl -I https://bilko.io → HTTP/2 200

Via Vercel CLI:

# List recent deployments
vercel ls --prod

# Promote specific deployment
vercel rollback <deployment-url>

Verification:

curl -I https://bilko.io
# Open bilko.io in browser — should show previous version

Estimated time: < 2 minutes


3.2 Backend Rollback (Railway) — < 5 minutes

Railway keeps the last 10 deployments.

Via Railway Dashboard (recommended):

  1. Open Railway Dashboard → Project → api service
  2. Click "Deployments" tab
  3. Find last successful deployment (look at deployment timestamp + status)
  4. Click "..." → "Redeploy"
  5. Wait for deployment to complete (~2 min)
  6. Verify health check

Via Railway CLI:

# List recent deployments
railway deployments list --service api

# Note the previous deployment ID
# Redeploy via dashboard (CLI redeploy not yet supported)

Pre-rollback — if migration was included:

If the broken release included database migrations, you must decide:

  • Option A (preferred): Write a forward-fix migration and deploy instead of rolling back
  • Option B: Database rollback (see 3.3) — use only if Option A is not possible

Verification:

curl https://api.bilko.io/health
# Expected: {"status":"ok","db":"ok","timestamp":"..."}

# Test auth
curl -X POST https://api.bilko.io/api/v1/auth/login \
  -H "Content-Type: application/json" \
  -d '{"email":"[email protected]","password":"test123"}'

Estimated time: < 5 minutes


3.3 Database Rollback — < 60 minutes

WARNING: Database rollbacks are destructive. Any data written since the bad migration WILL BE LOST.

Before rolling back database:

  1. Export all data created since the bad migration (if any):
    railway run psql $DATABASE_URL -c "
    COPY (SELECT * FROM invoices WHERE created_at > '[migration_time]') TO STDOUT;"
    
  2. Assess data loss: is losing this data acceptable?
  3. Prefer forward-fix migration if at all possible

If rollback is necessary:

# Step 1: Stop API traffic (put up maintenance page)
# Railway → api → Suspend

# Step 2: Restore from pre-deploy backup
# Railway Dashboard → PostgreSQL → Backups → Select backup taken before deploy

# OR restore from manual backup:
railway run psql $DATABASE_URL < pre_deploy_YYYYMMDD_HHMM.dump

# Step 3: Verify backup integrity
railway run psql $DATABASE_URL -c "SELECT COUNT(*) FROM invoices;"
railway run psql $DATABASE_URL -c "SELECT COUNT(*) FROM organizations;"

# Step 4: Redeploy previous backend version (without the bad migration)
# Railway → api → Deployments → Redeploy previous

# Step 5: Verify
railway run npx prisma db pull  # Should match backup schema
curl https://api.bilko.io/health

# Step 6: Resume API traffic
# Railway → api → Resume

# Step 7: If any data was lost, manually re-enter from exported data

Estimated time: 30–60 minutes


4. Rollback Verification Checklist

After any rollback, verify ALL of these before declaring rollback successful:

  • API health: curl https://api.bilko.io/health{"status":"ok","db":"ok"}
  • Frontend loads: https://bilko.io opens without errors
  • Login works: test account can authenticate
  • Invoice creation works: create test invoice, verify totals
  • VAT calculation correct: verify Serbia 20% on 1000 RSD = 200 RSD VAT
  • BetterStack: all monitors green
  • Sentry: no new error types
  • Database counts: record counts match pre-deploy snapshot (if DB rollback)

5. Rollback Communication

During Rollback

  1. Post in Slack #bilko-alerts immediately: "Initiating rollback — [reason]"
  2. Update status.bilko.io: "We are investigating an issue and reverting recent changes"
  3. Do not provide ETAs until rollback is verified successful

After Successful Rollback

  1. Post in Slack #bilko-alerts: "Rollback complete — previous version restored — investigating root cause"
  2. Update status.bilko.io: "Service restored — all systems operational"
  3. If any user impact: send email to affected organizations within 2 hours
  4. Create incident report within 24 hours

6. Version-Specific Rollback Notes

Release Frontend Tag Backend Tag DB Migration Included Rollback Notes
v1.0.0 Initial Initial 0001_initial_schema, 0002_indexes First release — no rollback possible

(Update this table with each release)


7. Rollback Testing

Each major release must include a rollback test on staging before production deploy:

# Deploy to staging
# ... (standard deploy)

# Test rollback on staging
vercel rollback  # Frontend
railway deployments redeploy <previous-id>  # Backend

# Verify staging is back on previous version
curl https://staging-api.bilko.io/health

Document rollback test results in deployment checklist.



Approval

Role Name Date Signature
Author Ops Architect 2026-02-23
Reviewer Tech Lead
Approver Alem Bašić