Skip to main content

Risk Register

Risk Register: {{PROJECT_NAME}}

Project: {{PROJECT_NAME}} Version: {{VERSION}} Date: {{DATE}} Author: {{AUTHOR}} Status: Draft | In Review | Approved Reviewers: {{REVIEWERS}}

Document History

Version Date Author Changes
0.1 {{DATE}} {{AUTHOR}} Initial draft

1. Risk Identification Methodology

Identification Methods Used:

  • Team brainstorming session (Date: {{DATE}}, Participants: {{PARTICIPANTS}})
  • Lessons learned review from previous projects
  • Risk category checklist (see Section 2)
  • Stakeholder interviews
  • Assumption analysis (see project charter)
  • Technical spike / proof-of-concept findings

Initial Risk Assessment Date: {{DATE}} Next Scheduled Review: {{DATE}} Risk Owner: {{RISK_OWNER}} (typically the Project Manager)


2. Risk Categories

Category Description Common Examples
Technical Technology failures, integration issues, performance, security API changes, infrastructure limits, unknown complexity
Resource Team availability, skill gaps, capacity constraints Key person sick leave, agent performance degradation
Client Client-side decisions, availability, requirement volatility Delayed approvals, changing priorities, unclear requirements
External Third-party dependencies, regulatory changes, market shifts API deprecation, GDPR change, competitor launch
Financial Budget overruns, payment delays, cost estimates Underestimated effort, currency exposure, vendor price change
Timeline Schedule risks, deadline pressure, estimation errors Milestone slip, hard deadline, dependency delays
Quality Defect rate, technical debt, process failures Insufficient testing, rushed delivery, poor documentation
Organizational Internal politics, process changes, leadership decisions Reprioritization, team restructure, tool changes

3. Risk Probability & Impact Scale

3.1 Probability Scale

Level Score Definition Example
Very Low 1 < 10% chance — rare, theoretical Unknown-unknown
Low 2 10–30% chance — unlikely but possible Historical precedent rare
Medium 3 30–50% chance — may occur Has happened on similar projects
High 4 50–70% chance — likely to occur Happens regularly
Very High 5 > 70% chance — almost certain Happened before on this type

3.2 Impact Scale

Level Score Schedule Impact Budget Impact Quality Impact
Negligible 1 < 1 day < 1% Minor fix needed
Minor 2 1–3 days 1–5% Some rework needed
Moderate 3 3–7 days 5–10% Significant rework
Major 4 1–2 weeks 10–20% Deliverable at risk
Critical 5 > 2 weeks > 20% Project failure risk

3.3 Risk Matrix (Probability × Impact)

         IMPACT →
         1(Neg) 2(Min) 3(Mod) 4(Maj) 5(Crit)
P  5(VH) |  5  |  10  |  15  |  20  |  25  |  ← CRITICAL ZONE (≥15)
R  4(H)  |  4  |   8  |  12  |  16  |  20  |
O  3(M)  |  3  |   6  |   9  |  12  |  15  |
B  2(L)  |  2  |   4  |   6  |   8  |  10  |  ← MEDIUM ZONE (5-14)
↑  1(VL) |  1  |   2  |   3  |   4  |   5  |  ← LOW ZONE (≤4)
Score Risk Level Response Required Escalation
1–4 LOW Monitor; review monthly PM awareness
5–9 MEDIUM Active mitigation plan required PM + Tech Lead
10–14 HIGH Immediate action + weekly review PM + John
15–25 CRITICAL Emergency response; may stop project John + Alem

4. Risk Appetite Statement

Overall Risk Appetite: {{LOW | MEDIUM | HIGH}}

Risk Category Appetite Rationale
Technical Medium Innovation requires technical experimentation
Financial Low Budget is fixed; overruns require CEO approval
Quality Low Client satisfaction is core to ALAI brand
Timeline Medium Some schedule flexibility acceptable if quality maintained
Security Very Low Zero tolerance for data breaches or compliance violations
Regulatory Very Low Legal exposure is unacceptable

Maximum Acceptable Risk Exposure: Score ≤ 9 without escalation to John. Escalation Threshold: Any risk scoring ≥ 10 must be reported to John within 24 hours.


5. Active Risk Register

ID Risk Description Category Prob (1-5) Impact (1-5) Score Response Strategy Owner Trigger Indicators Status Date Identified Review Date
R-001 {{RISK_DESCRIPTION}} Technical {{1-5}} {{1-5}} {{SCORE}} Mitigate {{OWNER}} {{TRIGGER}} Open {{DATE}} {{DATE}}
R-002 Key client contact unavailable for approvals Client 3 4 12 Mitigate PM Slow email responses; missed meetings Open {{DATE}} {{DATE}}
R-003 Third-party API deprecates required endpoint External 2 5 10 Mitigate Tech Lead Vendor changelog; API versioning notice Open {{DATE}} {{DATE}}
R-004 Scope creep from undiscovered requirements Client 4 3 12 Mitigate BA/PM Frequent "small" change requests Open {{DATE}} {{DATE}}
R-005 Performance targets not met under load Technical 3 4 12 Mitigate Tech Lead Slow response in dev testing Open {{DATE}} {{DATE}}
R-006 {{RISK_DESCRIPTION}} Open {{DATE}} {{DATE}}
R-007 Open
R-008 Open

6. Risk Response Strategies

Risk ID Strategy Response Actions Contingency Plan Resources Required
R-001 {{STRATEGY}} 1. {{ACTION_1}}; 2. {{ACTION_2}} {{CONTINGENCY_IF_RISK_OCCURS}} {{RESOURCES}}
R-002 Mitigate 1. Identify backup decision-maker; 2. Set approval deadlines in contract; 3. Async approval process Escalate to John → client sponsor PM time: 2h/week
R-003 Mitigate + Accept 1. Abstract API calls behind service layer; 2. Monitor vendor changelog; 3. Build integration tests Switch to alternative vendor; allocate 3-day buffer Tech Lead: 1 day setup
R-004 Avoid + Mitigate 1. Detailed BRD sign-off before development; 2. Formal change request process enforced; 3. Weekly scope review Raise change request; negotiate timeline/budget BA: 2h/week scope monitoring

Response Strategy Definitions

Strategy When to Use Action
Avoid High score + feasible to eliminate Change plan to remove the risk source
Mitigate Cannot avoid; must reduce probability or impact Implement controls, monitoring, early warning systems
Transfer Risk can be shared with third party Insurance, contractual liability transfer, outsourcing
Accept (Active) Low score; mitigation cost > risk cost Monitor and create contingency plan
Accept (Passive) Negligible score Acknowledge, no action required
Escalate Exceeds project authority or appetite Raise to John / Alem / client sponsor

7. Risk Heat Map

quadrantChart
    title Risk Heat Map — {{PROJECT_NAME}}
    x-axis Low Impact --> High Impact
    y-axis Low Probability --> High Probability
    quadrant-1 "CRITICAL — Immediate Action"
    quadrant-2 "HIGH — Active Management"
    quadrant-3 "LOW — Monitor"
    quadrant-4 "MEDIUM — Watch"
    R-001: [0.7, 0.5]
    R-002: [0.6, 0.5]
    R-003: [0.8, 0.3]
    R-004: [0.5, 0.7]
    R-005: [0.7, 0.5]

Update coordinates as Probability/Impact scores change. X = Impact/5, Y = Probability/5.


8. Escalation Thresholds

Threshold Action Responsible Timeframe
Any new risk Score ≥ 15 Immediate escalation to John + Alem PM Within 4 hours of identification
Any existing risk score increases by ≥ 5 Escalate to John PM Within 24 hours
> 3 risks at Score ≥ 10 simultaneously Emergency risk review meeting PM + John Within 48 hours
Any risk triggers its contingency plan Notify all stakeholders PM Immediately
Risk causes milestone slip > 3 days Formal change request + escalation PM Within 24 hours

9. Risk Review Schedule

Frequency Activity Participants Output
Weekly (Sprint Planning) Review all active risks, update scores/status PM, Tech Lead Updated register
Sprint Retrospective Identify new risks; close resolved risks Full team New risks added
Monthly Full risk register review + heat map update PM, John Risk report to stakeholders
Ad-hoc New risk identified (any time) Risk identifier + PM New risk logged within 24h
Milestone Risk review before each major milestone PM, Tech Lead, John Go/no-go input

Review Log

Date Reviewer Risks Reviewed New Risks Added Risks Closed Key Changes
{{DATE}} {{NAME}} {{COUNT}} {{COUNT}} {{COUNT}} {{SUMMARY}}

10. Closed / Accepted Risks Archive

ID Risk Description Resolution Type Resolution Notes Date Closed
R-999 Example: Third-party payment provider delays Mitigated Switched to backup provider; no impact {{DATE}}

Approval

Role Name Date Signature
Author
Reviewer
Project Manager
AI Director (John)
Project Sponsor