Risk Register
Risk Register: Drop — Fintech Payment App
Project: Drop — Remittance + QR Payments
Version: 1.1
Date: 2026-02-23
Author: John (AI Director)
Status: Active
Reviewers: Alem Bašić (CEO)
Document History
| Version |
Date |
Author |
Changes |
| 0.1 |
2026-02-08 |
legal agent + finance agent |
Initial 2-round risk identification |
| 1.0 |
2026-02-11 |
John |
Added technical risks from security audit |
| 1.1 |
2026-02-23 |
John |
Closed resolved risks; updated statuses |
1. Risk Identification Methodology
Identification Methods Used:
- 2-round multi-agent analysis (8 agents: legal, finance, security, dev, marketer, data-engineer, product, nicksaraev)
- Security audit (2026-02-11, John — 1,102 lines of API code reviewed)
- Regulatory risk checklist (PSD2, AML, GDPR, DORA — gap analysis in security/COMPLIANCE.md)
- Business case risk matrix (zica-business-case-v2.md section 10)
- Assumption analysis (project charter)
Initial Risk Assessment Date: 2026-02-08
Next Scheduled Review: 2026-03-01 (sprint planning)
Risk Owner: John (AI Director)
2. Risk Categories
| Category |
Description |
Common Examples |
| Technical |
Technology failures, integration issues, performance, security |
JWT secrets, SQLite limits, API race conditions |
| Resource |
Team availability, skill gaps, single points of failure |
Alem sole decision-maker, AI cost overruns |
| External |
Third-party dependencies, regulatory changes, market shifts |
BaaS partner, Finanstilsynet, Vipps competition |
| Financial |
Budget overruns, payment delays, cost estimates |
Grant approval delay, marketing burn |
| Regulatory |
Compliance failures, licence requirements, penalties |
PSD2 licence, AML, GDPR, PCI-DSS |
| Quality |
Defect rate, technical debt, process failures |
Security vulnerabilities, untested integrations |
3. Risk Probability & Impact Scale
3.1 Probability Scale
| Level |
Score |
Definition |
| Very Low |
1 |
< 10% chance |
| Low |
2 |
10–30% chance |
| Medium |
3 |
30–50% chance |
| High |
4 |
50–70% chance |
| Very High |
5 |
> 70% chance |
3.2 Impact Scale
| Level |
Score |
Schedule Impact |
Financial Impact |
| Negligible |
1 |
< 1 day |
< 1% budget |
| Minor |
2 |
1–3 days |
1–5% budget |
| Moderate |
3 |
3–7 days |
5–10% budget |
| Major |
4 |
1–2 weeks |
10–20% budget |
| Critical |
5 |
> 2 weeks |
Project failure |
3.3 Risk Matrix
| Score |
Risk Level |
Response Required |
Escalation |
| 1–4 |
LOW |
Monitor monthly |
PM awareness |
| 5–9 |
MEDIUM |
Active mitigation plan |
John awareness |
| 10–14 |
HIGH |
Immediate action + weekly review |
John escalation |
| 15–25 |
CRITICAL |
Emergency response |
John + Alem |
4. Risk Appetite Statement
Overall Risk Appetite: LOW (fintech — money movement requires high safety standards)
| Risk Category |
Appetite |
Rationale |
| Technical (security) |
Very Low |
Financial app — zero tolerance for data breaches |
| Regulatory |
Very Low |
GDPR, PSD2, AML violations have criminal penalties |
| Financial |
Low |
Fixed budget; overruns require Alem approval |
| External (BaaS) |
Medium |
Modular architecture allows provider swap |
| Timeline |
Medium |
Some schedule flexibility acceptable |
| Competition |
High |
Market risk accepted; innovation is our moat |
5. Active Risk Register
| ID |
Risk Description |
Category |
Prob (1-5) |
Impact (1-5) |
Score |
Response Strategy |
Owner |
Status |
Date Identified |
| R-001 |
BaaS partner (Swan or SpareBank1) not confirmed — blocks Phase 2 Open Banking integration |
External |
4 |
5 |
20 |
Mitigate |
Alem |
Mitigating — SpareBank1 pitched; Swan backup |
2026-02-08 |
| R-002 |
Finanstilsynet PISP/AISP registration delayed beyond planned timeline |
Regulatory |
4 |
5 |
20 |
Mitigate |
Alem + Legal |
Open — not started |
2026-02-08 |
| R-003 |
Security breach before production hardening complete |
Technical |
2 |
5 |
10 |
Mitigate |
John |
Mitigating — audit done; 8 critical fixes tracked |
2026-02-11 |
| R-004 |
Vipps launches competing remittance feature |
External |
3 |
4 |
12 |
Accept |
Alem |
Monitoring |
2026-02-08 |
| R-005 |
Slow merchant adoption — QR revenue below projection |
External |
3 |
3 |
9 |
Mitigate |
Alem |
Open — door-to-door strategy planned |
2026-02-08 |
| R-006 |
Hardcoded JWT_SECRET fallback active in production |
Technical |
2 |
5 |
10 |
Mitigate |
John |
Mitigating — fix tracked in Phase 0.5 |
2026-02-11 |
| R-007 |
CVV/card data exposed via GET API endpoint (PCI-DSS violation) |
Regulatory |
2 |
5 |
10 |
Mitigate |
John |
Mitigating — last_four only; fix in Phase 0.5 |
2026-02-11 |
| R-008 |
SQLite single-writer bottleneck at 200+ concurrent users |
Technical |
2 |
3 |
6 |
Accept |
John |
Accepted for MVP; PostgreSQL migration planned |
2026-02-13 |
| R-009 |
Alem is sole human decision-maker — decision bottleneck |
Resource |
3 |
3 |
9 |
Mitigate |
Alem |
Mitigating — decisions logged in comms/decisions/ |
2026-02-08 |
| R-010 |
KYC mock in production — AML compliance not active |
Regulatory |
2 |
5 |
10 |
Mitigate |
John |
Open — Sumsub production required before real money |
2026-02-13 |
| R-011 |
No real BankID — DOB proxy insufficient for SCA |
Technical / Regulatory |
2 |
4 |
8 |
Mitigate |
John |
Open — Phase 1 is demo only; BankID in Phase 2 |
2026-02-13 |
| R-012 |
In-memory rate limiter resets on process restart — brute force risk |
Technical |
2 |
4 |
8 |
Mitigate |
John |
Mitigating — DB-backed rate limits in Phase 0.5 |
2026-02-11 |
| R-013 |
No CSRF protection on state-changing API endpoints |
Technical |
2 |
4 |
8 |
Mitigate |
John |
Mitigating — CSRF middleware in Phase 0.5 |
2026-02-11 |
| R-014 |
Cash flow gap if Innovasjon Norge grant delayed |
Financial |
3 |
3 |
9 |
Mitigate |
Alem |
Monitoring — AI costs keep burn < 10K/month |
2026-02-08 |
| R-015 |
Race condition on concurrent remittance transactions (double-spend) |
Technical |
2 |
5 |
10 |
Mitigate |
John |
Mitigating — per-user transaction lock implementation |
2026-02-11 |
6. Risk Response Strategies
| Risk ID |
Strategy |
Response Actions |
Contingency Plan |
| R-001 |
Mitigate |
1. SpareBank1 pitch submitted; 2. Swan evaluated as backup; 3. Modular BaaS interface in architecture |
If neither works: explore Wio Bank, Finom, Treezor |
| R-002 |
Mitigate |
1. Engage external legal advisor for Finanstilsynet process; 2. Apply early; 3. Operate under bank partner licence initially |
If delayed: launch in limited beta under partner licence |
| R-003 |
Mitigate |
1. Security audit complete; 2. Phase 0.5 sprint fixes 8 critical issues; 3. No real money in MVP |
If breach occurs: incident response plan in security/incident-response.md |
| R-004 |
Accept |
Monitor Vipps announcements monthly; accelerate community adoption |
Emphasise 0.5% vs Vipps fees; focus on trust advantage |
| R-005 |
Mitigate |
1. Door-to-door onboarding; 2. 0% fee for first 3 months; 3. 200-merchant target Month 12 |
Adjust fee structure; focus on high-volume corridors |
| R-006 |
Mitigate |
1. JWT_SECRET required env var — fail fast; 2. Secrets via Vaultwarden |
Rotate secrets immediately; force re-auth |
| R-007 |
Mitigate |
1. Remove CVV from GET response; 2. Store only last_four + token_ref; 3. Tokenisation via card partner |
Suspend cards feature until fixed |
| R-010 |
Mitigate |
1. Sumsub integration contract; 2. Mock clearly gated by feature flag; 3. No real money until KYC live |
Suspend onboarding until KYC active |
| R-015 |
Mitigate |
1. Per-user transaction lock (in-process); 2. DB-level constraint as backup; 3. PostgreSQL advisory locks in Phase 2 |
Suspend concurrent transactions; queue-based processing |
7. Risk Heat Map
quadrantChart
title Drop Risk Heat Map — 2026-02-23
x-axis Low Impact --> High Impact
y-axis Low Probability --> High Probability
quadrant-1 "CRITICAL — Immediate Action"
quadrant-2 "HIGH — Active Management"
quadrant-3 "LOW — Monitor"
quadrant-4 "MEDIUM — Watch"
R-001 (BaaS partner): [1.0, 0.8]
R-002 (Finanstilsynet): [1.0, 0.8]
R-004 (Vipps): [0.8, 0.6]
R-003 (Security): [1.0, 0.4]
R-006 (JWT): [1.0, 0.4]
R-007 (CVV): [1.0, 0.4]
R-015 (Race condition): [1.0, 0.4]
R-009 (Alem bottleneck): [0.6, 0.6]
R-014 (Cash flow): [0.6, 0.6]
R-008 (SQLite): [0.6, 0.4]
8. Escalation Thresholds
| Threshold |
Action |
Responsible |
Timeframe |
| Any new risk Score ≥ 15 |
Escalate to Alem + John |
John |
Within 4 hours |
| Any existing risk score increases by ≥ 5 |
Escalate to John |
John |
Within 24 hours |
| > 3 risks at Score ≥ 10 simultaneously |
Emergency risk review |
John + Alem |
Within 48 hours |
| Risk triggers contingency plan |
Notify all stakeholders |
John |
Immediately |
| Risk causes milestone slip > 3 days |
Formal change request |
John |
Within 24 hours |
9. Review Schedule
| Frequency |
Activity |
Participants |
Output |
| Weekly (Sprint Planning) |
Review all active risks, update scores |
John |
Updated register |
| Sprint Retrospective |
New risks identified; closed risks archived |
John |
New risks logged |
| Monthly |
Full register review + heat map |
John, Alem |
Risk report |
| Milestone |
Risk review before go/no-go |
John, Alem |
Go/no-go input |
Review Log
| Date |
Reviewer |
Risks Reviewed |
New Added |
Closed |
Key Changes |
| 2026-02-08 |
legal + finance agents |
— |
6 |
0 |
Initial identification |
| 2026-02-11 |
John (security audit) |
6 |
10 |
0 |
Added R-006 through R-015 |
| 2026-02-23 |
John |
15 |
0 |
5 |
Closed R-C01 to R-C05; updated statuses |
10. Closed Risks Archive
| ID |
Risk Description |
Resolution Type |
Resolution Notes |
Date Closed |
| R-C01 |
Wallet/balance model requires e-money licence |
Avoided |
Pivoted to PSD2 pass-through model (ADR-003) |
2026-02-12 |
| R-C02 |
FontelePay tightly coupled to Drop — regulatory risk |
Avoided |
Separated to own module (ADR-002) |
2026-02-12 |
| R-C03 |
Zica brand name has cultural sensitivity |
Avoided |
Rebranded to Drop (Alem decision 2026-02-09) |
2026-02-09 |
| R-C04 |
"Banking" language in UI creates regulatory exposure |
Mitigated |
Removed all "banking" references from UI (task #197) |
2026-02-09 |
| R-C05 |
SHA-256 password support creates rainbow table vulnerability |
Mitigated |
SHA-256 support removed; bcrypt-only policy enforced |
2026-02-13 |
Approval
| Role |
Name |
Date |
Signature |
| Author |
John (AI Director) |
2026-02-08 |
Approved (AI) |
| Reviewer |
John (AI Director) |
2026-02-23 |
Reviewed |
| AI Director (John) |
John |
2026-02-23 |
Approved |
| Project Sponsor |
Alem Bašić |
TBD — requires review |
|