PLOCK — Gaps and Next Steps
Date: 2026-03-14
Purpose: Convert the current PLOCK reality into an actionable plan: what is missing, what is conflicting, what is risky, and in which order the remaining work should happen.
1. Goal
The original goal was to get PLOCK into a state where we can:
- understand the real product and architecture,
- produce deterministic documentation,
- QA that documentation,
- then generate implementation tasks by feature area,
- and move toward demo-readiness / production-readiness in a controlled way.
This document defines what blocks that goal today and what sequence should be followed next.
2. Current State Summary
PLOCK already has:
- substantial real code,
- real integrations,
- real tests,
- real infrastructure scaffolding,
- real product and GTM documentation.
However, PLOCK is currently blocked by:
- conflicting architecture documentation,
- missing canonical documentation package,
- weak documentation-to-artifact execution flow,
- and lack of a clean, approved “source-of-truth → QA → backlog” chain.
3. Gap Categories
3.1 Canonical Documentation Gaps
GAP-DOC-001 — Canonical docs/demo-readiness/ package exists, but is still incomplete
Severity: P0
The canonical demo-readiness package now exists, but it is still only a baseline layer.
Already present:
- source-of-truth baseline
- user stories baseline
- feature baseline
- gaps/next-steps baseline
- QA checklist baseline
Still missing or incomplete for the fuller package:
-
program map
-
deterministic task contract
-
doc inventory gap audit
-
package-level review expansion
-
later demo/sales/support readiness docs
-
program map
-
deterministic task contract
-
doc inventory gap audit
-
user stories baseline
-
feature catalog
-
QA gate checklist
Impact:
Without this package, there is no stable documentation handoff point for QA or implementation backlog generation.
GAP-DOC-002 — No canonical feature catalog
Severity: P0
Features are spread across:
- code structure,
- PRD,
- GTM docs,
- API spec,
- runbooks,
- integration docs.
But there is no single authoritative feature catalog that says:
- what exists,
- what is partial,
- what is planned.
Impact:
Implementation task generation will drift or duplicate work.
GAP-DOC-003 — User stories are present, but not operationalized
Severity: P1
User stories exist mainly in docs/PRD.md, but not yet in a clean, implementation-ready canonical user-story document.
Impact:
Traceability between product vision and implementation work is weaker than it should be.
GAP-DOC-004 — Canonical QA checklist exists, but QA execution is still incomplete
Severity: P0
A trusted QA checklist now exists, but the review process is still immature and must continue with explicit review records and package verdicts.
What now exists:
- deterministic QA checklist baseline
- package review workflow
What still needs strengthening:
- continued document-by-document review records as the package grows
- repeatable reviewer discipline for future generated docs
- explicit re-review after any canonical doc changes
Impact:
QA can now start approving or rejecting the documentation layer, but the process still depends on careful manual review.
3.2 Architecture / Source-of-Truth Gaps
GAP-ARCH-001 — Conflicting architecture documents
Severity: P0
docs/ARCHITECTURE.md conflicts with the actual repo and stronger docs.
Examples of stale/conflicting claims:
- Next.js instead of MFE shell
- Express instead of Ktor
- Prisma instead of Exposed + Flyway
organization_idinstead ofwarehouse_id
Impact:
Any agent or human using the wrong document can generate incorrect output.
GAP-ARCH-002 — API spec drift
Severity: P1
docs/API-SPEC.md appears useful, but likely drifted from the actual backend implementation and tenant model.
Impact:
API-facing work may be built or reviewed against incorrect assumptions.
GAP-ARCH-003 — Runbook drift
Severity: P1
Different docs disagree on:
- npm vs pnpm
- startup flow
- JDK/runtime expectations
Impact:
Ops/docs/support/demo execution can become inconsistent and brittle.
3.3 Product / Feature Gaps
GAP-FEAT-001 — AI feature maturity unclear
Severity: P1
AI Chat and Smart Picking are core product promises, but actual implementation depth is not yet cleanly verified against code and runtime behavior.
Impact:
Demo promises may exceed current product maturity.
GAP-FEAT-002 — 3PL capability is more strategy than current product
Severity: P1
3PL/client portal/billing appears strongly in docs and GTM, but current implementation evidence suggests this is more Phase 2 than current MVP.
Impact:
Sales/demo scope can overpromise if not constrained.
GAP-FEAT-003 — Sales/marketing/support artifacts not packaged
Severity: P2
The content exists in fragments:
- GTM strategy
- pricing
- regulatory notes
- runbooks
But not yet as:
- demo script,
- objection handling pack,
- support playbook,
- onboarding checklist,
- sales-facing feature matrix.
Impact:
Cross-functional readiness is incomplete.
3.4 Security / Hygiene Gaps
GAP-SEC-001 — Secret-like material in infra docs
Severity: P0/P1
infrastructure/README.md contains environment variable examples that resemble real secrets or secret material.
Impact:
Security hygiene issue. Must be reviewed and cleaned immediately.
GAP-SEC-002 — Secrets/process docs need explicit verification pass
Severity: P1
Secrets strategy exists, but should be validated against:
- actual deployment practice,
- Vaultwarden usage,
- Railway variable setup,
- non-committed local env discipline.
Impact:
Production readiness risk if docs and reality differ.
3.5 Process / Orchestration Gaps
GAP-PROC-001 — Delegated doc output quality remains unreliable
Severity: P0
Even after improving task gating, agents still often:
- narrate output,
- claim files were created,
- fail to produce actual artifacts.
Impact:
Important documentation work cannot yet be trusted blindly.
GAP-PROC-002 — Contradictory orchestration logging still exists
Severity: P1
Observed behavior:
- task blocked by QA gate,
- then orchestrator still logs it as completed.
Impact:
Operational trust and status reporting are still imperfect.
GAP-PROC-003 — Forge worker pool saturation
Severity: P1
Some tasks are delayed or requeued because:
- forge pool is full,
- H-priority tasks compete with unrelated workload.
Impact:
Even correctly defined tasks may not progress quickly.
4. What Must Happen Before Feature-by-Feature Implementation Tasks
Before generating backend/frontend/db/integration/security/sales/marketing task waves, we need:
Required Preconditions
- canonical source-of-truth note
- canonical user stories baseline
- canonical feature baseline
- canonical gaps/next-steps note
- canonical QA checklist
- clear exclusion of stale architecture doc from planning
- security hygiene review of infra secret examples
If these are skipped, implementation tasks will be generated against mixed truths.
5. Recommended Execution Order
Phase 1 — Documentation Truth Lock
Priority: P0
Deliverables
- Canonical source-of-truth note
- User stories baseline
- Feature baseline
- Gaps and next steps
- QA checklist baseline
Outcome:
One trusted planning layer.
Phase 2 — Documentation QA
Priority: P0
QA should validate the documentation set against:
- actual repo structure
- actual code domains
- actual migrations
- actual integrations
- actual security/tenant model
QA must explicitly check:
- no stale architecture assumptions
- no references to nonexistent files
- no contradictory stack descriptions
- no unsupported feature claims
- every feature mapped to status: exists / partial / planned
Outcome:
Trusted doc package.
Phase 3 — Controlled Backlog Generation
Priority: P1
Once the doc package passes QA:
- generate backend task list
- frontend task list
- DB/data task list
- integration task list
- security task list
- sales/marketing/support task list
Rules for backlog generation
Every generated task must include:
- exact output contract
- exact deliverable path or target
- acceptance check
- source references
- explicit feature/user-story linkage
Outcome:
Deterministic implementation backlog.
Phase 4 — Demo Readiness Pass
Priority: P1
Once the controlled backlog exists:
- create demo script
- create UI/demo journey map
- create sales narrative
- create support/onboarding flow
- create go/no-go checklist
Outcome:
Real demo package, not vague “prod-ready” claims.
Phase 5 — Production Readiness Pass
Priority: P2
Only after docs + QA + controlled backlog + demo prep:
- ops readiness verification
- secrets/process cleanup
- observability checks
- deployment validation
- test coverage/reliability review
- support and incident readiness
Outcome:
Production-readiness based on evidence, not optimism.
6. Immediate Next Actions
NOW-001 — Freeze stale architecture usage
- Treat
docs/ARCHITECTURE.mdas stale - Do not use it for planning or QA
NOW-002 — Clean security hygiene issue
- Review and sanitize
infrastructure/README.md - Assume secret-like values may need rotation review
NOW-003 — Finalize canonical documentation baseline
- source-of-truth
- user stories
- feature baseline
- gaps/next steps
- QA checklist baseline
NOW-004 — Do not launch broad implementation waves yet
- no broad backend/frontend/db waves
- no mass task fan-out based on stale or mixed docs
NOW-005 — Generate only narrow, deterministic tasks
Until process reliability improves, every task should be:
- narrow,
- artifact-bound,
- source-referenced,
- QA-verifiable.
7. Success Condition
We are ready to resume the original plan when all of the following are true:
8. Decision
PLOCK should proceed through a documentation-truth-first path, not a broad parallel execution wave.
This is not extra process for its own sake.
It is the minimum needed to ensure the next backlog is based on the real product rather than conflicting documentation or fabricated agent output.